Technical Clarifications for Green Star represent our answers to Technical Questions submitted by projects, and provide further guidance and reference to others. The list is regularly updated.  

There are two types of Technical Clarifications listed in the table below:

General Clarifications

These are extensions to the guidance provided in the Submission Guidelines. They clarify and sometimes supersede the original Credit Criteria or 
Compliance Requirements. General Clarifications set precedent for future project teams to follow. Should a project team wish to apply a general clarification to its project, there is no requirement for further Technical Questions to be submitted. NZGBC Assessors will also use them as precedents to assess submissions.

Project Specific Clarifications

These are published as references for other projects but, unlike General Clarifications, they do not set precedent. They often relate to special 
situations where multiple prerequisites exist for a particular project and are less likely to reoccur to another project. Therefore, rulings set for Project Specific Clarifications are often conditional and will likely vary for other projects. Each project still needs to submit its own Technical Questions and provides evidence relating to its own building in order to have a similar ruling approved for that specific building. 

Should you wish to apply any Technical Clarification for legacy rating tools to your projects, please submit a Technical Question to the NZGBC to 
explain why and how it applies. You can access the online Technical Question form here

Technical Question Title Tool Version Date Released Credit Name Sub-credit Name TC Link
Default Design Occupancy DABv1, DABv1.1 November 2022 0 - General General
Approved Ruling:

The use of default Design Occupancy from Green Star Legacy tools is not an acceptable method of calculating Design Occupancy for speculative developments.  For speculative developments it is common for the developer / client to provide a Building Performance Specification or similar document which outlines the development’s requirements for the design team. The Design Occupancy referred to in the Building Performance Specification or similar should be used consistently as the basis for calculations for all relevant credits.