 Green Star Technical Clarification Rulings

Technical Clarifications for Green Star represent our answers to Technical Questions submitted by projects, and provide further guidance and reference to others. The list is regularly updated.  

There are two types of Technical Clarifications listed in the table below:

General Clarifications

These are extensions to the guidance provided in the Submission Guidelines. They clarify and sometimes supersede the original Credit Criteria or 
Compliance Requirements. General Clarifications set precedent for future project teams to follow. Should a project team wish to apply a general clarification to its project, there is no requirement for further Technical Questions to be submitted. NZGBC Assessors will also use them as precedents to assess submissions.

Project Specific Clarifications

These are published as references for other projects but, unlike General Clarifications, they do not set precedent. They often relate to special 
situations where multiple prerequisites exist for a particular project and are less likely to reoccur to another project. Therefore, rulings set for Project Specific Clarifications are often conditional and will likely vary for other projects. Each project still needs to submit its own Technical Questions and provides evidence relating to its own building in order to have a similar ruling approved for that specific building. 

Should you wish to apply any Technical Clarification for legacy rating tools to your projects, please submit a Technical Question to the NZGBC to 
explain why and how it applies. You can access the online Technical Question form here

Technical Question Title Tool Version Date Released Credit Name Sub-credit Name TC Link
High Quality Staff Support DABv1 October 2019 7 - Responsible Construction Practices High Quality Staff Support
Approved Ruling:

Can a single program or initiative be used to comply with High Quality Staff Support?

Yes, providing the program or initiative covers at least three distinct issues, with one of the three specifically addressing mental health impacts. For points to be awarded, project teams must clearly highlight the distinct issues and provide evidence in the submission demonstrating these being addressed on site.

As outlined in the Submission Guidelines, issues addressed may be, but are not limited to, the following:.

  • healthier eating and active living
  • reduced harmful alcohol and drug and tobacco-free living
  • increase social cohesion, community, and cultural participation
  • understanding depression
  • preventing violence and injury
  • suicide prevention
  • decreased psychological distress

The following is a brief (but not exhaustive) list of programs and initiatives which could be implemented on site for, made available to, or discussed with all construction workers for the duration of construction. Each program may cover one or more distinct issue/s as required by the credit.  Evidence must be provided for each issue addressed by a program.

  • Beyond Blue
  • Mates in Construction
  • Lifeline
  • Headspace
  • White Ribbon
  • Nutrition Organisation